First section: 28" 1.5 km long pipeline. We dewatered it and achieved a dewpoint of -40 degrees with the use of our nitrogen unit.

Second section: 48" 47km long pipeline. Bigger pipeline, bigger pump and again a dewpoint of -40 degrees was achieved.

Third section: 48" 137km long pipeline dewatered and achieved the desired dewpoint.

Fourth and last section: 48" 143km long pipeline this line was also dewatered and a dewpoint was achieved within the client's expectations.

328.5 Kilometres!